Issue 5 Timeline

On November 6, Dublin City Schools registered voters approved Issue 5, a ballot initiative designed to address the District's rapid enrollment growth, as well as maintenance and upgrades at existing facilities
 
Since 2007, the District has added more than 2,700 students and more than 3,000 are expected over the next 10 years. Below is a general timeline of some of the large scale Issue 5 projects and some associated items
Summer 2019
Maintenance and security upgrades at existing schools
 
Additional mental health professionals hired prior to the 2019-20 school year
 
Renovation of Central Office into a centralized preschool begins (Central Office moves to the 4th floor of Emerald Campus)
 
Fall 2019
Elementary redistricting committee begins work and will complete its task prior to winter break
 
Middle school naming committee makes recommendation to the Board of Education
 
Emerald Campus third floor open for students
 
Ceremonial groundbreaking for Middle School 5
 
Construction of Middle School 5 begins
 
Summer 2020
Maintenance and security upgrades at existing schools
 
Portables removed from Deer Run and Pinney
 
Fall 2020
Two elementary schools open for students, Hopewell on Bright Road and Abraham Depp in Jerome Village 
 
Centralized preschool opens at former Central Office building
 
Middle school redistricting committee begins its work and will complete its task prior to winter break 
 
Summer 2021
Maintenance and security upgrades at existing schools 
 
Fall 2021
Middle School 5 opens in Jerome Village
 
 
 
 
 
 