Issue 5 Timeline

  • On November 6, 2018, Dublin City Schools registered voters approved Issue 5, a ballot initiative designed to address the District's rapid enrollment growth, as well as maintenance and upgrades at existing facilities.

    Since 2007, the District has added more than 3,000 students and more than 3,000 are expected over the next 10 years. Below is a general timeline of some of the large scale Issue 5 projects and some associated items.

    The District recently completed a build-out study that indicates our enrollment growth will continue until about 2036. You can view the build-out study at this link.

    Below is the timeline in place for upcoming construction projects and facility openings as of the fall of 2019. This timeline is subject to change.

    Summer 2019

    Maintenance and security upgrades at existing schools

    Additional mental health professionals hired prior to the 2019-20 school year

    Renovation of Central Office into a centralized preschool begins (Central Office moves to the 4th floor of Emerald Campus)

    Fall 2019

    Elementary redistricting committee begins work and will complete its task prior to winter break

    Middle school naming committee makes recommendation to the Board of Education

    Emerald Campus third floor open for students

    Ceremonial groundbreaking for Middle School 5

    Construction of Middle School 5 begins

    Summer 2020

    Maintenance and security upgrades at existing schools

    Portables removed from Deer Run and Pinney

    Fall 2020

    Two elementary schools open for students, Hopewell on Bright Road and Abraham Depp in Jerome Village

    Centralized preschool opens at former Central Office building

    Summer 2021

    Maintenance and security upgrades at existing schools

    Fall 2021

    Middle School 5 opens in Jerome Village